Encore Hotel Barnsley Case Study.

Case Study added September, 2009

Another project completed to the highest quality for the Encore Hotel Junction 37 M1 in Barnsley South Yorkshire.

Click the images below for larger versions.

Development: Encore Hotel

Location: Barnsley

Description of work: With work in full swing on the De Vere at Leeds we started works on the Ramada Encore Hotel at Barnsley, this is a 120 bedroom hotel complete with conference facilities, as ever our dedicated team of decorators strived to complete on time while maintaining our high standards of workmanship.

Main Contractors: ISG PLC

Architects: Humphrey Cook Associates Architects

Work Commenced:August 2008

Work Completed: November 2008

Manpower: maximum of 12 men on site at any one time.